Question 2: The Work Breakdown Structure of a project is
given in the following table.
Activity
|
Immediate Predecessors
|
Average Time in days
|
Variance
|
A
|
None
|
20
|
100
|
B
|
None
|
10
|
50
|
C
|
None
|
40
|
80
|
D
|
A
|
15
|
70
|
E
|
A
|
50
|
30
|
F
|
B
|
15
|
0
|
G
|
C
|
20
|
55
|
H
|
D
|
30
|
45
|
I
|
E
|
25
|
60
|
J
|
C,F
|
35
|
90
|
K
|
G
|
10
|
30
|
L
|
H
|
25
|
20
|
M
|
J,K
|
30
|
55
|
Only 115 days are available to complete this project. What
is the probability that this project will get completed within the given time?
What will be the impact on probability if another 10 days are added to the
available time?
20 marks
Answer: Watch this Video